WaterSolve was tasked to remove sediment from 2 ponds owned by a homeowners association. Mechanical excavating near homes was not an option, so divers were subcontracted to go into pond and harvest the sediment. The customers was very happy with results and offered to be a reference in the future.

DOWNLOAD PDF Applications & ProductsPolymers, Geotextile Tube Containers, ServicesDewatering, Complete Solutions, Turnkey Project ManagementIndustryMarine DewateringLocationOhio, USA

OVERVIEW

Watersolve LLC, was tasked to remove the sediment from two ponds owned by a homeowner’s association in Southern Ohio and transfer the residual to a lot owned by the developer. The ponds were located near homes and mechanical excavating was not an option. Divers went into the pond and harvest the sediment with a 4” suction hose. The sediment was then pumped in a 6” pipeline to the disposal site. WaterSolve treated the sediment in the pipeline with a cationic polymer to speed up the settling and clear up the water so it could be pumped back to the pond or released to a waterway near the disposal site.

CHEMICAL CONDITIONING

A representative sample of pond sediment was tested by a technician in the WaterSolve lab. Dewatering polymers were evaluated based on water release rate, water clarity, and flocculent appearance. In addition, dosing rate(s) were determined during bench-top dewatering experiments and recommendations provided to the homeowner’s association during this phase of the program. Solve 137 was the recommended polymer for dewatering this residual in this settling application. The results of this testing indicated a flow of 8% dry wt. solids of the residual from the ponds would require 100-ppm of the Solve 137 polymer.

THE RESULT

WaterSolve LLC was contracted by the homeowner’s association to remove the sediment from two ponds and transfer it to a disposal site owned by a developer. The developer had agreed to have a dam built at the lower end of a watercourse to contain the sediment and allow the solids to settle. This served as the disposal site. Divers were subcontracted to enter the ponds and manipulate a 4” suction hose to remove the sediment. A 6” diesel pump transferred the sediment 1400’ to the disposal site. Solve 137 polymer was injected into the 6” hose transferring the sediment to the disposal site. Solve 137 flocculated the solids and sped up the settling process. This allowed the water to be returned to the ponds or pumped to a nearby waterway. A polymer make-down unit was used to activate the polymer by diluting it with water and meter in the proper dose. A WaterSolve technician was present to adjust the polymer dose based on visual observations of pail samples taken from an inline sample port. The ponds had a maximum depth of 10’ with 5’ of sediment is some areas. One of the ponds was stocked with fish and divers used full diving gear with supplied air to enter the pond and remove the sediment. The water table was lowered in the other pond, and the divers used dry suits to enter the pond and gather the sediment. Approximately 600 cubic yards of sediment was removed in 5 days which included moving the equipment from pond to pond one time. The project manager for the homeowner’s association was very happy with the results and offered to be a reference if needed.