A city in Colorado needed to remove biosolids from a WWTP lagoon which was no longer in service. The plan was to use a hydraulic submersible pump to remove the biosolids from the lagoon and pump them into Geotube® containers for dewatering. The biosolids would then be allowed to dewater in the Geotube® containers, before being excavated and removed for disposal. The city would self perform the project, with WaterSolve, LLC personnel on site for project start-up and training.
DOWNLOAD PDF Applications & ProductsGeotextile Tube Containers, DewateringServicesComplete Solution, Turnkey Project ManagementIndustryMunicipalLocationColorado, USA
A city in Colorado needed to remove biosolids from a WWTP lagoon which was no longer in service. The plan was to use a hydraulic submersible pump to remove the biosolids from the lagoon and pump them into Geotube® containers for dewatering. The biosolids would then be allowed to dewater in the Geotube® containers, before being excavated and removed for disposal. The city would self perform the project, with WaterSolve, LLC personnel on site for project start-up and training.
Geotube® containers are manufactured from high strength polypropylene fabric and designed to allow effluent water to escape through the pores of the fabric while retaining the chemically conditioned solids. Estimates based on information provided by the city indicated approximately 2,200 cubic yards of biosolids would need to be removed in order to achieve project goals. It was determined that two Geotube® containers (60 ft. circumference x 200 ft. long) would be needed to dewater this volume of biosolids.
A sample of the lagoon biosolids was sent to WaterSolve’s lab for preliminary testing. Based on laboratory testing, Solve 127 was determined to flocculate and dewater the residual most effectively compared to the other products. Water clarity and flocculent appearance were good to excellent when an 4-mL (133-ppm/4.2-lbs per dry ton) dose was added to a 150-mL sample.
WaterSolve LLC, was contracted by a city in Colorado to assist with project startup and training of city personnel. This included providing a liner, Geotube® containers, filtration fabric, a cationic polymer, a polymer feed system, and technical assistance. Watersolve prepared a layout drawing showing recommended dimensions and grading for the laydown area where the Geotube® containers would be placed. The city had the grading of the laydown area completed prior to our arrival. Upon arrival at the site, a 15-mL liner was laid in the containment area and secured around the edges. Filtration fabric, which assists with drainage between the Geotube® containers and the liner, was placed on the liner. The Geotube® containers were unrolled and 6” hoses were plumbed into the fill ports. The polymer feed system was placed between the lagoon and the Geotube® containers. The polymer feed unit selected for this project is capable of providing up to 10 gallons per hour of neat polymer. The drum of Solve 127 polymer was plumbed to the polymer feed unit and the made-down polymer supply line was plumbed into a 6” mixing manifold as part of the pipeline. The submersible pump was suspended in the lagoon with a 6” discharge pipeline exiting the lagoon and connecting to the mixing manifold. When the pumping began, initial solids content was low. Sampling of the treated material indicated a low dose of flocculating polymer was needed to treat the material. Solids content of the material increased as the project progressed. Continual visual monitoring of the treated material resulted in adjusting of the dosing rate as the solids content increased. The WaterSolve technician was on site for the first four days of the project to assist with operations and train city personnel that would be in charge of monitoring the dewatering aspect of the project for the remainder of the project. Operations continued until the lagoon cleanout was complete.