This rural town in Montana had a buildup of biosolids in the primary aeration lagoon at their wastewater treatment facility. The state required them to select a method and reduce the biosolids to get the lagoon operating as it was designed. Dredging to the Geotube® container’s provided an excellent solution to deal with the large amount of debris in the lagoon.
DOWNLOAD PDF Applications & ProductsDredging, Geotextile Tube Containers, DewateringServicesComplete SolutionIndustryMunicipalLocationMontana, USA
The primary aeration lagoon at this small town in Montana had a buildup of biosolids and the state required them to remove a quantity that would get the system performing properly. There was a significant amount of debris in the lagoon as the town didn’t have a good screening system to prevent it from entering the lagoon. The objective was to dredge the biosolids from the lagoon with the least amount of stoppage and dewater it for subsequent hauling to a landfill. Geotube® dewatering was selected to meet the criteria. As long as the dredge can pump the debris and biosolids, the Geotube® can dewater it. The process also offered storage of the material until funds became available to dispose of it in a landfill.
While on a site visit to the WWTP, a WaterSolve technician tested the biosolids with several polymer emulsions. Chemical conditioning with Solve 137 was determined to flocculate and dewater the residual most effectively compared to the other products. Water clarity and flocculent appearance were good to excellent when an 8.6-mL (288-ppm/19.2-lbs per dry ton) dose was added to a 150-mL sample.
Geotube® containers are manufactured from high strength polypropylene fabric and designed to allow effluent water to escape through the pores of the fabric while retaining the chemically conditioned solids. Estimates based on sampling by an outside engineering firm indicated 1.35 million gallons of the 3% (dry wt. solids) biosolids would need to be pumped in order to achieve project goals. It was determined that three Geotube® containers(45ft. Circumference by 100ft. long, 60ft. Circumference by 100ft. long, and 75ft. Circumference by 100 ft. long) were needed to dewater this quantity of biosolids.
Watersolve LLC, was contracted by the municipality to manage the project. This included providing a liner, Geotube® containers and filtration fabric, a cationic polymer, a polymer feed system, and technicians for the dredging and dewatering. SRS Crisafulli was contracted by WaterSolve to provide and operate the electric dredge. A containment pad for the Geotube®’s had been prepared by an excavation firm from a drawing prepared by WaterSolve’s engineers. Upon arrival at the site a 20-mL liner was laid in the Geotube® containment pad and secured around the edges. Filtration fabric was placed on the liner to allow drainage between the Geotube® containers and the liner. The Geotube® containers were unrolled on the pad and 6” hoses were plumbed into the fill ports. The polymer feed system was placed between the lagoon and the Geotube® pad. The polymer feed unit is capable of providing up to 30 gallons per hour of neat polymer. The tote of Solve 137 polymer was plumbed to the polymer feed unit and the made-down polymer supply line was plumbed into a 6” mixing manifold as part of the dredge pipeline. Meanwhile the dredge was placed in the lagoon with a 6” discharge pipeline exiting the lagoon and connecting to the mixing manifold.
When the dredging began there was approximately 600-gpm of flow to the Geotube® containers and the dredge pace across the pond had to be slowed as the biosolids were too thick to treat properly. After this first pass across the lagoon the dredge was vibrating and when the cutterhead was exposed, there was a lot of debris in the pump and cutterhead. From that point on the dredge was stopped after each pass to remove debris from the cutterhead and pump. The WaterSolve technician stayed in radio contact with the dredge operator to communicate the solids flow and get maximum performance from the system. The tubes were filled to maximum capacity 4 times throughout the project and the met the quantities specified in the contract.