| Oldham County Stone Quarry |
The stormwater retention basin at Oldham County Stone
Quarry overflowed its banks and flooded two adjacent mine
shafts secured by the Department of Defense for records
and materials storage. A site survey estimated that approximately
18,000 cubic yards of aggregate sediments @ 40% dry weight
solids had accumulated in the basin, decreasing its storage
capacity by greater than 50%. The objective of this project
was to dredge the stormwater retention basin to its bedrock
bottom and simultaneously increase the stormwater retention
basin’s berm height by seven feet, protecting Department
of Defense storage shafts from future flooding events.
Kentucky Dredge and WaterSolve were contracted by Rogers
Group to dredge 18,000 cy of aggregate sediments from
their stormwater retention basin and dewater the residuals
in 1,100 linear feet of 45’ circumference Geotubes®
located between the basin and storage shafts. Sediments
were chemically conditioned (Solve 9350) in-line with
WaterSolve’s WSLP-2400USF and initially dredged
into four Geotubes® (45’ circ. x 100’
long) @ 850 gpm over three days.
|
|
| Light Industrial Wastewater
Treatment Plant |
WaterSolve, LLC was tasked to evaluate a light industrial
facility's lagoon sludge (Elwood, IL) for a chemical conditioning
program and potential use of Geotubes® for containment,
dewatering, and either landfill disposal or land application
of sludge cake as an alternative to their current residuals
management strategy. WaterSolve completed installation
of three 60’ circ. x 100’ long Geotube®
containers, temporary piping, and polymer make-down &
feed equipment in May 2006. Liquid residuals at 2.0 to
4.0% dry wt solids were chemically conditioned (300 ppm
of Solve 9248) and pumped into the three Geotubes®
over 60 d. The facility consolidated and dewatered 1.0
MG of residuals for approximately $0.04/gallon (without
disposal costs) after this first year of operations. Geotube®
dewatering applications were an economical and operational
option for this industrial facility, providing a four
season alternative to their current management strategy.
|
|
|
| Michels Corporation and
Lunda Construction Inc. |
WaterSolve identified a dual polymer chemical conditioning
program and subsequent application of Geotube® containers
for containment and dewatering of construction and mining
residuals during pipeline installation. Filtrate from
the Geotube® treatment system met State discharge
permit limits and allowed for continuous operations of
all three drilling sites for the term of this project.
In addition, Michels and Lunda were able to contain and
dewater a full year of residuals production into one Geotube®
container at each site and minimize excavation and hauling
costs.
|
|
| City of Ligonier, IN Municipal WWTP |
An alternative method for containment and dewatering
was sought by the Ligonier, IN WWTP contract manager (EMC),
that not only reduced the costs associated with biosolids
processing but required less facility resources to operate.
Biosolids from this facility were traditionally dewatered
with six drying beds and a truck-mounted belt press was
rented twice a year at an annual cost of $45,000.00 to
dewater the remaining biosolids from a 275,000-gallon
storage tank. WaterSolve completed installation of a Geotube®
container, temporary piping, and polymer make-down &
feed equipment in June 2005. Heavy sludge (275,000 gallons)
at 5-6% solids was chemically conditioned (Solve 9248)
and pumped into the Geotube® container over three
days. As a result of WaterSolve and EMC’s resolve,
the municipality will save nearly $25,000.00 after this
first year of operations with the first Geotube® container
and greater than $35,000.00 annually in subsequent years.
|
|
| City of Cambridge,
OH Municipal WWTP |
Approximately 1 MG of sludge (4-6% solids) was pumped,
contained, and dewatered from the Cambridge WWTP using
Miratech’s
Geotube® Dewatering Technology and polymer (WaterSolve).
Cake solids (20% solids) were excavated and transported
to the local landfill after 45-d of drying, saving the
city valuable time and money while pouring and storing
biosolids simultaneously.
|
|
| Lake Michigan Water Filtration Plant |
WaterSolve teamed up with a local contractor to perform
a pump-out of an infiltration basin at Lake Michigan Water
Filtration Plant that was clogged with 9,000 cy of alum
sludge. Compared to previous dewatering operations, dewatering
with eight 60’ x 100’ Geotube®
Containers to > 50% solids reduced the cost of
disposal by 60%.
|
|
| City of Eatonton, GA Municipal
WWTP |
Eight 30’ x 50’ Geotube®
Containers and polymers are being used annually to
contain and dewater 3 MG of municipal biosolids (1% solids)
at the city of Eatonton, GA’s two 350,000 gpd wastewater
treatment plants. The city chose Miratech’s Geotube®
Dewatering Technology for rapid removal of solids
because it offers high volume containment, effective filtration,
extremely high quality effluent, 85% reduction of BOD
in the effluent, no capital expenditure, no special equipment,
and was easy to operate by existing staff.
|
|
City of Escabana, MI Water Filtration Plant
|
As part of the normal water treatment process, the City
of Escanaba used aluminum sulfate to sequester impurities
in the raw water prior to disinfection and distribution
throughout the City’s drinking water system. On
a normal basis, this sequestered material would collect
in the bottom of the filtration tank until the excess
required removal. Infrastructure Alternatives and WaterSolve,
LLC utilized 45’ circumference and 30’ circumference
Geotube®
Containers as part of a pilot study to determine the
viability of the Geotube®
Dewatering Technology as a dewatering process for
the alum sludge. The pilot study was so successful that
upon design for a plant upgrade project, Geotube®
Containers were implemented into the permanent process
for the water treatment plant.
|
|
| [Geotube®
is a registered trademark of TenCate Nicolon] |